🏗️ Contract Costing – Meaning, Features & Profit Calculation
This post explains the concept of contract costing, its features, types of contracts, how it is different from job costing, and how profits are estimated on incomplete contracts. It also includes short notes and important past exam questions.
📑 Table of Contents
- What is Contract Costing?
- Features of Contract Costing
- Contract Costing vs Job Costing
- Cost Plus Contract
- Profit Determination on Incomplete Contracts
- Short Note: Escalation Clause and others
- Important Questions
📘 What is Contract Costing?
Contract costing is a special form of job costing used for ascertaining cost and profit on contracts undertaken for big jobs like constructing a building, a road, a bridge or a ship. Such jobs mainly comprise activities outside the contractor’s premises and involve huge amount. They take long time to complete so much so that the work may extend over more than one accounting year. This means that the cost and profit may have to be worked out even on incomplete work as at the end of an accounting year. Hence, a special method of accounting known as ‘contract costing’ or ‘terminal costing’ has been developed for ascertaining cost and profit on such jobs.
📌 Features of Contract Costing
The distinguishing features of contract are as follows:
Features regarding Production
i) The work is undertaken to customer’s specific requirements.
ii) The work will be of a relatively long duration and involves large amount.
iii) The work is usually site based.
iv) The work is frequently of a constructional nature.
v) Plant and equipment may be purchased or hired for the duration of the contract.
vi) The completion date is fixed in advance, and penalties follow delays.
vii) Certain aspects of the work are assigned to sub-contractors.
Features regarding Cost
i) The cost unit in contract costing is a contract.
ii) A separate account is prepared for each contract to ascertain the profit or loss on each contract.
iii) Most of the items of cost can be classified as direct since they can be easily identified with a specific contract.
iv) Indirect costs are normally restricted to Head Office expenses and storage costs. These are allocated to various contracts on which work is carried out during the year.
v) The contract price is often fixed in advance and payment is received at various stages of completion based on architect’s certificate.
vi) A separate contract ledger is maintained for recording costs when the number of contracts is large.
🔍 Contract Costing vs Job Costing
The principals involved in contract costing are the same as those
involved in job costing. Certain modifications are to be made in the
principles, in some cases, to suit the requirements of particular contracts. In
spite of same principles, contract costing differs from job costing on same
points mentioned below:
1. Number of jobs in hand at a time may be much greater than the number
of contracts in hand at a time.
2. Most of the items of expenses are capable of being directly charged
to contract accounts; but direct charging to that extent is not possible in
case of jobs.
3. Collection, analysis, apportionment or allocation of cost is
simpler in contract costing than in job costing.
4. In case of contracts taking a number of years to complete the
question of assessment of profit at the end of each financial year crops up.
This question does not arise in case of job costing.
5. Normally, contracts are executed outside the factory, i.e., at
customer’s site; but jobs are executed within the factory.
💰 Cost Plus Contract
Where the contractee agrees to pay the contractor, as contract price,
the exact cost plus certain percentage thereof to cover overhead expenses and
profit, the contract is called cost plus contract.
In case of new type of work where the contractor cannot estimate the
cost due to lack of experience in the line, cost plus contract is generally
entered into. Government contracts are often on cost plus contract basis.
Since in these contracts the contractor is assured of reimbursement of
actual cost, there is no initiative on the part of the contractor to economize.
Higher cost means higher profit. So, the contractor is interested in higher
cost. On the part of the contractee, therefore, higher supervision cost is
involved. The fixed percentage of margin allowed sometimes becomes inadequate
and sometimes it becomes excessive.
Main features of cost-plus-contracts:
1. This method is adopted in the case of those
contracts where the probable cost of contract cannot be ascertained in advance
with a reasonable accuracy.
2. These contracts are preferred when the cost of
material and labour is not steady and contract completion may take number of
years.
3. The different costs to be included in the
execution of the contract are mutually agreed so that no dispute may arise in
future in this respect. Under such type of contract contractee is allowed to
check or scrutinize the concerned books, documents accounts.
4. Such a contract offers a fair price to the
contractee and also a reasonable profit to contractor.
5. The contract price here is ascertained by adding
a fixed and mutually pre-decided component of profit to the total cost of the
work.
Costs plus contracts have the following advantages:
a) The contractor is assured of a fixed percentage of profit. There is
no risk of incurring any loss on the contract.
b) It is useful especially when the work to be done is not
definitely fixed at the time of making the estimate.
c) Contractee can ensure himself about “the cost of the contract”, as he is
empowered to examine the books and document of the contractor to ascertain the
veracity of the cost of the contract.
📈 Profit on Incomplete Contracts
If the work on a contract is
started and finished during the same accounting year, its profit or loss can be
easily calculated and transferred to Profit and loss Account. But, in case of
contracts which extend to more than one accounting year, the question arises
whether any profit or loss should be accounted for during the accounting year
or years when they are still in progress and, if so, how?
It is agreed that if profit is
computed only on the competition of the contract, there will be heavy
fluctuation in the amount of profit from year to year. This will result not
only in distorted profit pattern but also higher tax liability during the year
of completion of the contract because the tax will have to be paid at higher
rates. At the same time, if profit is computed on the uncompleted contracts and
taken to Profit and Loss Account, there is a possibility of other unforeseen
contingencies. Hence, it is an accepted principle that profit on uncompleted
contracts must be taken into account in respect of the work certified only
after providing adequate reserve for future contingencies.
Rules relating to estimating
profit / loss on incomplete contracts
(i) If completion of contract is less than 25%, no profit should be
taken to Profit and Loss account.
(ii) If completion of contract is up to 25% or more but less than 50%,
then 1/3 × Notional Profit × (Cash received / Work certified) may be taken to
Profit and Loss account.
(iii) If completion of contract is 50% or more but less than 90%, then 2/3
× Notional Profit × (Cash received / Work certified) may be taken to Profit and
Loss account.
(iv) If completion of contract is greater than or equal to 90%, then one
of the following formulas may be used for taking the profit to Profit and Loss
account:
- Estimated Profit × (Work certified / Contract price)
- Estimated Profit × (Work certified / Contract price) × (Cash received
/ Work certified)
- Estimated Profit × (Cost of the work to date / Estimated total cost)
- Estimated Profit × (Cost of the work to date / Estimated total cost) ×
(Cash received / Work certified)
- Notional Profit × (Work certified / Contract price)
📄 Short Note: Escalation Clause
Short Note on Escalation Clause
This clause is usually provided in the contracts as a safeguard against
any likely changes in the price or utilization of material and labour. If
during the period of execution of a contract, the prices of materials or labour
rise beyond a certain limit, the contract price will be increased by an agreed
amount. Inclusion of such a term in a contract deed is known as an 'escalation
clause'
An escalation clause usually relates to change in price of inputs, it
may also be extended to increased consumption or utilization of quantities of
materials, labour etc. In such a situation the contractor has to satisfy the
contractee that the increased utilization is not due to his inefficiency.
📚 Important Questions - job, Contract and Process Costing
Q. Explain the features, advantages and disadvantages of job costing.
Q. What is process costing? What are the fundamental principles of Process Costing? Point out the advantages and limitations of Process costing. 2019
- Preparation of process accounts together with normal, abnormal loss and abnormal gain account, preparation of profit and loss account and costing profit and loss account, treatment of process finished stock and stock of raw material in process accounts. Follow examples of BASU AND DAS COST ACCOUNTING BOOK. 2013, 2016, 2018
- Preparation of contract account
Post a Comment
Kindly give your valuable feedback to improve this website.