2021/TDC (CBCS)/ODD/ BBACC-501T/171
TDC (CBCS) Odd Semester Exam., 2021 held in March, 2022
BUSINESS ADMINISTRATION
(5th Semester)
Course No.: BBACC-501T
(Quantitative Techniques for Management)
Full Marks: 70
Pass Marks: 28
Time: 3 hours
The figures in the margin indicate full marks for the questions
SECTION – A
Answer any ten questions: 2 x 10=20
1. What is meant by linear programming problem?
2. Define the term decision variables' in the context of LPP.
3. How do you find pivot element' from a simplex tableau?
4. What do you mean by transportation problem?
5. Mention any two methods for finding the initial basic solution in a transportation problem.
6. What is meant by degeneracy in a transportation model?
7. Mention the uses of project evaluation review techniques.
8. What is meant by critical path method?
9. Distinguish between total float and free float.
10. What is meant by Pay-off table?
11. What is an opportunity loss table?
12. What is meant by expected monetary value?
13. What is meant by two-person zero-sum game?
14. Distinguish between pure and mixed strategies.
15. What is meant by saddle point?
SECTION – B
Answer any five questions: 10 x 5=50
16. Solve the following LPP using graphical method:
Maximize z = 2x + 3y;
Subject to constraints
x + y £ 30; x £ 20, y £ 12 and x, y ³ 0.
17. Solve the following LPP using simplex algorithms:
Maximize z = 40x1 + 30x2
Subject to constraints
x1 + x2 £ 12
2 x1 + x2 £ 16
x1, x2 ³ 0
18. Distinguish between the steps involved to find initial basic solution by North-West corner rule and least cost method.
19. Five warehouses are supplied by four factories. The supply available from each factory, the demand at each warehouse and the cost per unit of transporting goods from factories to the warehouses are summarized in the following table:
|
Warehouse Factory |
W1 |
W2 |
W3 |
W4 |
W5 |
Supply |
|
F1 |
13 |
9 |
15 |
10 |
12 |
40 |
|
F2 |
11 |
10 |
12 |
12 |
9 |
10 |
|
F3 |
12 |
9 |
13 |
12 |
9 |
20 |
|
F4 |
13 |
12 |
13 |
12 |
10 |
10 |
|
Demand |
12 |
15 |
20 |
15 |
18 |
Use North-West corner rule to find initial basic solution.
20. Write a note on the steps involved to determine the earliest starting time and earliest finishing time in critical path analysis.
21. The following details are available regarding a project:
|
Activity |
Predecessor activity |
Duration |
|
A |
- |
3 |
|
B |
A |
5 |
|
C |
A |
7 |
|
D |
B |
10 |
|
E |
C |
5 |
|
F |
D.F. |
4 |
Determine the critical path and the project completion time.
22. Discuss the application of decision theory analysis in business.
23. Calculate the EMV for each courses of action from the pay-off matrix below:
|
States of Nature |
Probability |
Course of Action |
||
|
A1 |
A2 |
A3 |
||
|
N1 |
0.70 |
0 |
6,000 |
12,000 |
|
N2 |
0.20 |
30,000 |
6,000 |
12,000 |
|
N3 |
0.10 |
60,000 |
36,000 |
12,000 |
Also recommended the course of action to be adopted.
24. Discuss the application of game theory in business.
25. Explain with example the steps involved in the calculation of saddle point.
***
Post a Comment
Kindly give your valuable feedback to improve this website.